What goes on a punch list
A punch list covers work that's already in the job's
scope of work but isn't finished or isn't right
yet. Each item is small on its own. Together they decide whether the
customer signs off. Typical items:
- Remodels and electrical: missing cover plates, a crooked fixture, a
panel directory that doesn't list the new circuit, a wall scuffed during
the install.
- HVAC: the line set cover not on yet, the thermostat not set up, the
old unit still sitting by the driveway.
- Plumbing: caulk at a new tub, a missing trim ring at a shower valve, a
slow drip at a shutoff.
- Roofing: nails left in the lawn, a downspout to reattach, debris on
the patio.
Write each item with where it is, what's wrong and who will fix it, and add
a photo so nobody argues later about which scuff was meant.
How to run the closeout
- Walk it yourself first. The crew lead checks the job against the
scope before the customer sees it and fixes what they can that day. Every
item you catch is one the customer never has to find.
- Walk it with the customer. Go room by room or side by side and write
every item down where they can see it.
- Agree the list is complete. Get a signature or a text reply
confirming it. Anything raised after that is a new request or a warranty
question, not part of this list.
- Book the return visit before you leave, with the parts on the truck.
- Close it in writing. Send a photo of each finished item, get the
customer's sign-off and send the final invoice the same day.
Example: A $9,000 bathroom remodel has $900 due at completion. At the
walkthrough the customer lists six items: a towel bar not yet hung, two
caulk touch-ups, a cabinet door that rubs, a paint scuff and leftover tile
boxes in the garage. Your installer clears all six in a two-hour visit the
next morning, texts a photo of each, gets "looks great" back and sends the
final invoice from the driveway. Leave the list open for three weeks and
the $900 waits three weeks too.
Punch items, change orders and callbacks
Keep three things apart, because each one is handled differently:
- Punch item: in the original scope, not done or not right. You fix it
at no charge, before final payment.
- New request: something that wasn't in the scope, like a second outlet
or a different faucet. Write a change order with
a price and get it approved before you do the work.
- Problem after sign-off: a callback or a
workmanship warranty claim, tracked
separately from the job so you can see what it costs you.
Common mistakes
- No written list. A list that lives in someone's memory grows every
time someone walks through the house.
- New scope slipping in as punch items. Saying yes on the spot feels
easier, but unpriced extras come straight out of the job's margin.
How to handle change orders covers
how to price and approve them instead.
- One back-ordered part holding up the whole final payment. Agree on an
amount to hold back for that one item and invoice the rest now.
- An open-ended return visit. "We'll swing by next week" turns into a
month, and so does the final payment.
How it connects
On a job billed in stages with
progress billing, the punch list stands
between you and the last payment. On work under a general contractor, open
punch items can keep your retainage from being
released, so clear yours before the GC's final walk.
How to get paid faster covers the rest of
the path from finished job to paid invoice.