Write an electrical estimate after a site visit, from the panel out. State the load calculation behind any service upgrade or EV charger, list the work circuit by circuit with breaker types and device counts, and say who pulls the permit, who books inspections and who schedules the utility disconnect and reconnect. Exclude patching and painting in writing, price likely code-triggered upgrades as conditions in advance, and give the price an expiration date because wire and equipment costs move.
Electrical work comes in three shapes, and each needs a different estimate:
The expensive surprises on electrical work sit in the panel, the service and the walls, so the estimate is only as good as your site notes. Capture:
Every item on that list can change your price if you find it after the customer signs.
Any estimate that adds a large load or changes the service should show how you know the service can carry it. That covers EV chargers, heat pumps, electric ranges and water heaters, hot tubs, and feeders to a detached garage or an accessory dwelling.
The basis is the load calculation method in the edition of the National Electrical Code (NFPA 70) your jurisdiction enforces, along with any local amendments. Run the calculation with the new load included, keep the worksheet in the job file, and put a short summary on the estimate:
If you based the existing load on the utility's demand history or a recorded load study instead of a calculation, say which and attach it. Confirm first that your inspector accepts that approach under the code edition they enforce.
The summary shows that a service upgrade comes from math, not a sales pitch, which matters when another bid skipped the upgrade. And if your building department wants load calculations with the permit, it sees the same numbers the customer saw.
When the service can't carry the new load as designed, show every honest way forward. For an EV charger that usually means a lower charger setting where the charger's instructions allow one, load management equipment your inspector accepts, or a service upgrade. Put them in one table with the same scope, exclusions and conditions, so only the real differences show.
Example: A hypothetical EV charger estimate on a house with a 100-amp service, where the attached load calculation shows the charger won't fit at full output. Prices are round placeholders, not market rates:
Option 1 Option 2 Option 3 Approach Charger circuit, charger set lower Charger circuit plus load management device 200-amp service upgrade plus charger circuit Charging speed Reduced Full when the house allows Full Utility involvement None None Disconnect, reconnect, possible service request Power outage Short Short Most of a day Price $1,400 $2,200 $6,500 The $4,300 step from Option 2 to Option 3 buys full-speed charging at all times plus spare capacity for future loads, and the customer can decide whether that's worth it.
If a rebate or credit program comes up, list it under the price as something the customer may qualify for, never as a discount already taken.
The circuit schedule is the heart of an electrical estimate: it makes bids comparable and settles "I thought that was included" later. For each circuit, write:
| Column | What to write |
|---|---|
| Circuit | What it feeds and where, such as "EV charger, garage" or "island receptacles, kitchen" |
| New or extended | A new home run from the panel, or an extension of an existing circuit |
| Breaker | Size and type (standard, AFCI, GFCI or dual-function) and the panel space it uses |
| Wiring method | Cable or conduit, and the route: attic, basement, exterior wall, trench |
| Devices | Receptacles, switches, fixtures and boxes, counted by room |
| Supplied by | You or the customer, for fixtures, fans and chargers |
| Walls | Open framing, or finished surfaces you'll fish through |
Three columns deserve extra care:
If the customer hasn't chosen fixtures, carry a per-fixture allowance and say the difference will be billed or credited. For customer-supplied fixtures and chargers, say your warranty covers your labor and the product's is the manufacturer's, and what happens if one arrives damaged or unsuited to the location, such as an indoor fixture meant for a covered porch. The exclusions below belong to the same scope of work.
Give the permit its own line, say who pulls it, and list the inspections the job needs. Which electrical work requires a building permit, who may pull it and what the inspector checks are set by your state, your local building department or both. If you're unsure who can pull a permit for a given job, ask your state's electrical licensing board.
On the estimate, state:
On remodels with a rough-in inspection, tell the customer and the general contractor in writing that walls stay open until your rough-in passes. Drywall hung over uninspected wiring is a cost somebody pays; the estimate makes sure it isn't you.
If your jurisdiction adopts a newer NEC edition before you apply for the permit, ask which edition the job will be inspected under, and reprice anything it adds.
A service change needs the utility. The conductors ahead of the main breaker can only be de-energized on the utility's side, the utility usually owns the meter, and it sets rules for the equipment you connect to its system. The estimate should separate your work from the utility's and say who schedules each step.
Before you quote one, read the utility's service requirements, including its rules for the meter socket, mast and clearances, and learn how it handles each step below: the notice it needs, what it charges, and whether a larger service needs its review or changes to its transformer, drop or lateral.
| Step | Who handles it | What the estimate says |
|---|---|---|
| Service request or application | You, or the customer where the utility requires | Who files it, and any utility fee |
| Disconnect and reconnect | The utility, at your request | The date window and the expected outage |
| Meter and seal | Whoever the utility's rules allow | Who pulls and resets the meter |
| Service drop or lateral | The utility or the owner, depending on the utility | Whose work it is and who pays |
| Inspection release | The inspector and the utility | That reconnection follows the approved inspection where required |
| Trench for an underground service | You, unless excluded | Utility locates before digging, and restoration terms |
Tell the customer when the power will be off and for how long, and ask what depends on it: refrigerators and freezers, medical equipment, a sump pump, a home office, a security system, a garage door. Write the planned window into the estimate with a line that the utility's schedule can move it.
Electrical work makes holes. Say in writing what you leave behind and what you don't do:
One kind of sealing stays in your scope. Where your work passes through a fire-rated wall, floor or ceiling, ask your inspector how they want the penetration sealed and include it. That's part of the installation, not cosmetic patching.
Opening an old panel or a finished wall is where electrical jobs change. Say on the estimate what happens when you find something: you stop, show the customer photos, price the fix and get written approval first. Better still, price the common finds in advance, so the customer approves those prices when they sign.
Finds worth pricing ahead on service, panel and remodel work:
Example: A conditions schedule on a hypothetical panel replacement, with round placeholder prices:
If we find What we'll do Price Grounding electrode system the inspector won't pass Install what the inspector requires $500 A circuit that needs AFCI or GFCI protection under the enforced code Install the required breaker $100 per circuit Damaged conductors at the panel Splice or extend in a new box $150 per circuit Meter socket the utility rejects Replace the meter socket $700 If the crew finds two circuits that need new protection, the customer has already approved $200 for that, and the job keeps moving.
Anything not on the schedule goes through a written change order before the work.
Electrical estimates carry materials whose prices move: copper wire and cable, service equipment, panels, breakers and generators. Date every estimate, give it a validity window, and say on the page what happens to the price after that:
Example: Hypothetical wording: "Prices are valid for 30 days and are based on our supplier's quote of October 6. If you accept after that, wire and service equipment will be repriced from the supplier's invoice, and we'll show you the difference before we order." Say the wire was priced at $1,200 and costs $1,380 when the customer accepts in week six. The wire line goes up $180, backed by the supplier's invoice, instead of coming out of your margin.
An expiration date also gives you a reason to check in before it lapses; how to follow up on quotes covers the timing.
The last page turns the estimate into a contract:
You can give a range from photos of the panel label, the breakers with the panel door open, the meter and the parking spot, plus the charger model and a description of the route. Label it as a photo-based estimate, list what would change the price (the load calculation, the route, the panel's condition) and confirm on site before you commit to a fixed price.
Walk the customer through your load calculation summary and suggest they ask the other contractor for the calculation behind their number. If your options table includes a lower charger setting or load management, point to it: the customer may not need the upgrade, and your estimate already shows how to avoid it honestly. Don't criticize the other contractor; let the numbers make the case.
One document is fine, but give the upgrade and the charger circuit their own lines or options. The customer sees what the upgrade costs on its own, and if they decide to wait on the charger, or a rebate program wants the panel work itemized, you don't have to rewrite the estimate.