Write a plumbing estimate fixture by fixture: what you'll install, replace or move, approximate pipe lengths, how you'll reach the pipe and how long the water will be off. Give every fixture the customer hasn't chosen a written allowance, list the permit and inspections, and price possible code items as conditions. Name exclusions such as wall repair and concealed conditions, attach camera findings to sewer and drain estimates, show repipe materials side by side and state how changes get approved in writing.
A repair estimate fits on one screen: what failed, what fixes it, what it costs and how long the price holds. A project estimate (a water heater replacement, a repipe, a sewer line, a remodel rough-in) is also the document you'll point to when something unexpected turns up inside a wall or under a slab, so it has to define the job precisely.
If you can't see enough to define the job, don't guess. Sell the diagnosis first (a camera inspection, a leak locate or an exploratory opening) and write the estimate from what you found. Pricing is covered in how to price plumbing jobs; this guide covers what goes on the page.
Customers think in rooms; plumbers bid in fixtures and pipe. A complete scope of work names every fixture and connection the job touches and what happens to each one.
| Item | What to write |
|---|---|
| Each fixture | Install new, replace, reconnect, relocate or leave as is |
| Stops and supply connectors | Replaced or reused, fixture by fixture |
| Drain and vent | Tie in, extend or reroute, with the pipe material |
| Water heater | Fuel type, capacity, location and venting, old and new |
| Appliance connections | Dishwasher, ice maker, washer and gas appliances, in or out |
| Outdoor | Hose bibs and irrigation tie-ins |
| Main shutoff and pressure-reducing valve | Working, replaced or excluded |
Then write down the three things that drive plumbing labor:
On remodels, separate rough-in from trim, and say what (tile, countertops) must be finished before you set fixtures.
Finally, name the existing parts you're relying on. An old shutoff that won't close, or a stop that leaks once you turn it, can stall a job in its first hour, so add: "If an existing shutoff valve fails to close or leaks when operated, its replacement will be priced and approved before work continues." Problems you notice outside your scope, such as a corroded drain you weren't asked to replace, go on the estimate as observed and not included.
When the customer hasn't picked a faucet, toilet or shower trim, write an allowance: a dollar amount the price includes for that fixture, with the difference charged or credited once they choose. Each allowance line should state:
Plumbing allowances also have fit problems, so put the checks on the estimate:
If the customer supplies fixtures, price installation only and say plainly that you don't warranty the fixture itself, that missing or damaged parts mean a return trip at your normal charge, and who hauls away the old fixtures and packaging.
Example: A bathroom estimate includes a $300 toilet allowance and a $250 faucet allowance (round numbers for the math). The customer picks a $420 toilet and a $190 faucet. The toilet is $120 over and the faucet is $60 under, so the price goes up by $120 minus $60, or $60, approved in writing before you order.
Find out which jobs need a building permit in each jurisdiction you work in, checking at least water heater replacements, repipes, sewer and water service replacements, gas piping and any fixture you add or move, and build the answers into your template. On the estimate, state:
Pull the permit yourself. The FTC lists a contractor asking the homeowner to get the required building permits among the signs of a home improvement scam 1, so an estimate that leaves permits to the customer reads as a warning, not a saving.
The inspector judges your new work against the plumbing code enforced now, which may be newer than the one the house was built under. Depending on where you work, that's a version of a model code such as the International Plumbing Code or the Uniform Plumbing Code, or a state-written code, often with local amendments, so learn which edition each building department has adopted.
Before you price, list what the job could bring into play and decide whether each item is included or a priced condition:
If an item depends on the inspector's call, write it as a conditional line with its price, so the customer approves it up front.
Example: A gas water heater replacement is priced at $2,000 (a placeholder) with the expansion tank included. Two conditional lines follow: "If the inspector requires the vent connector replaced, add $250. If a drain pan with a drain line is required, add $150." If neither applies, the price stays $2,000. If both do, it's $2,000 + $250 + $150 = $2,400, and the customer saw that ceiling before signing.
Plumbing disputes often start with a hole: who patches it, and who pays for what was behind it. Name exclusions specifically:
In homes built before 1978, EPA's renovation rule requires anyone paid to disturb painted surfaces to be certified and trained in lead-safe work practices 2, so check whether it applies to the walls you'll open before you price the openings.
Then add a concealed-conditions clause: "Conditions hidden in walls, floors, slabs or underground, such as rotted framing, cracked drains, corroded fittings or earlier work that doesn't meet code, are not included. If we find one, we'll stop, photograph it and give you a written price before continuing, except for steps needed to stop an active leak or make the system safe." On slab leaks, give the reroute and the repair through the slab as separate options, each with its own concrete, flooring and restoration terms.
On sewer and drain work the customer can't see the problem, so the footage is your evidence. Attach the video or a link, still frames of each defect and a short findings summary:
Example: A hypothetical summary: "Inspected from the front cleanout. Clay pipe to 40 feet, plastic from there to the main. Roots at a joint at 22 feet, locator depth about 5 feet. Offset joint holding water at 36 feet. Camera stopped at 58 feet; the rest of the line was not seen."
Tie each recommendation to a finding. If you offer more than one fix, list each as an option with what it does and doesn't address: cleaning and root cutting, a spot repair at a located defect, full replacement, or lining or bursting where you offer it and the jurisdiction accepts it. In the example above, a spot repair at 22 feet leaves the offset at 36 feet, and the option should say so.
Before any digging, find out from the local sewer authority where the owner's responsibility for the line ends, call 811 for utility locates and build the wait into the start date, and say what surface restoration is included. 811 reaches your local one-call center, the marking is free, and PHMSA notes that state laws require the call 48 to 72 hours before digging 3; your state's law sets the exact notice period.
Repipe customers have usually heard opinions about pipe materials. Your estimate's job is to make the options comparable, not to win the argument. Keep the shared scope identical (fixtures served, patching terms, permit and testing) and show what differs the same way for each option:
| Row | What to write for each option |
|---|---|
| Material | PEX type and connection system, or copper type (such as Type L or Type M) and joining method |
| Routing | Home-run manifold or trunk and branch, and where the lines run |
| Openings | Expected number and rooms |
| Schedule | Days on site, and hours without water each day |
| Manufacturer warranty | Term, and conditions such as using that maker's fittings |
| Your warranty | The labor term you offer |
| Price | Total, and the date it expires |
Describe each material by the facts that matter for this house, and leave out claims you can't back up. Follow each manufacturer's installation instructions, such as PEX limits on sunlight exposure and on connections at the water heater, and price what they require. Copper prices move, so give copper options a shorter expiration or a material price clause.
Either way, say whether the price includes the main from the meter or well tank, new fixture stops, water heater connections, hose bibs, ice maker and laundry, and what happens to the old pipe. If plastic is replacing metal water pipe, list a check of the home's electrical grounding and bonding by a licensed electrician, included or excluded.
Plumbing jobs change for three reasons: the customer adds or upgrades, you find something hidden, or the inspector requires something that wasn't listed. Say on the estimate how all three are handled:
Pre-price the changes you expect: a rate per additional foot of sewer pipe beyond the measured length, per extra access opening, per added fixture stop. When the customer has already seen the number, approval is quick. What a change order contains and how to bill it is in how to handle change orders.
The last page turns the estimate into a contract. Include:
When you sell a repipe or a water heater at the kitchen table, the FTC's Cooling-Off Rule can apply. For sales of $25 or more at the buyer's home, the buyer can cancel until midnight of the third business day after the sale, and Saturday counts as a business day 4. A customer who called you out is still covered: the rule's definition includes sales made "in response to or following an invitation by the buyer" 5.
Plumbing has real emergencies, and the rule has a narrow exception for them: the buyer initiated the contact, the work is needed to meet a bona fide immediate personal emergency, and the buyer gives you a separate, dated and signed statement in their own handwriting that describes the emergency and waives the right to cancel 5. A burst pipe the customer called you about may fit. The repipe you recommend afterward doesn't, so write the emergency repair as its own job and the repipe as a normal contract with full cancellation rights. Your state may add its own home solicitation rules, so have a lawyer review your contract and cancellation forms.
That's a business decision, but tell the customer before the visit. One workable split: keep estimates free for planned work you can scope on a walk-through, such as a water heater replacement or a fixture swap, and charge for diagnostic work that produces findings on its own, such as a camera inspection or a leak locate. If you credit that fee when the customer hires you, say so in writing.
For a simple, well-defined task you can quote your flat rate or a range, as long as the written estimate after the visit is the price that counts. For anything involving pipe you can't see, such as a slab leak, a sewer line or a repipe, wait until you've inspected and explain why: access, lengths and existing conditions set the price.
Itemize the scope either way, so the customer can see what the price buys and compare it with other bids. Prices on each base line are optional, but always show separate prices for options, allowances and conditional code items, because those are the numbers that change after the customer signs.
Rules and figures change, and many requirements vary by state and city. Check the current version of each source and your local authority before acting, and talk to a licensed professional about your specific situation.